Progress to Nov 2, 2017:-
Site Set Up Complete
Demolition Complete
Main Hall Foundations and Slab Complete
Dampproofing to Main Hall complete
Foundation insulation to Main hall complete.
Installation of Main Hall Floor Joists commenced.
- site progress to Nov 2, 2017